LS-100 & LS-200 Drill Rig
Assembly Instructions

Before you
begin assembling the LS-100, unpack the shipping crate in a secure, dry, clean
area to ensure that all the parts are still in the crate.
When assembling or repairing the LS-100 and mud pump, it is
helpful to make reference to Figure 1 below which shows the various components of
the LS-100.
- Remove Base (11) from the crate and install stabilizer tubes (9) and secure with set screws
(10). Remove Mast Assembly (1) from crate and install onto Base with the 1/2-inch bolts (12)
using a lock-washer under each head.
- Remove Rotary Assembly (4) & (5) from carton. Place assembly on the shuttle bracket (6)
while guiding the 2 bolts into the hinges.
- Note that the push-pull type throttle comes installed. If the throttle keeps retracting, ensure that the throttle spring on the engine has been removed.
- Connect side Entry Swivel to 3 way Valve with short 5' Hose Assembly (3).
- Connect the by-pass hose to the nipple in the bottom of the 3-way valve.
- Connect the mud pump discharge hose to the side port of the 3-way valve.
- Connect the mud pump suction hose to the suction port of the pump and place the foot valve in the suction pit.
Figure 1: LS-100 Assembly
Back to LS-100 Main Page
|